List of Projects under Tenaga National Berhad (TNB)

No.
Project
Job Scope
Main Contractor
Job Status
1
Kg. Pandan - 275kV
GIS Installation
Trangrip Sdn. Bhd.
Completed, Nov 2018
2
Semantan - 132/33kV
GIS & Transformer Installation
Duta Technik Sdn. Bhd.
Completed, Sep 2018
3
KL North - 275kV
2 Sets of Circuit Breaker Replacement Work
GE Services Sdn. Bhd.
Completed, Jan 2019
4
PMU - 132/33kV Cochcrane GIS
Installation GIS & Transformer
PESB Engineering Sdn. Bhd.
Completed, Mar 2021
5
PMU 132/33kV Ayer Puteh
Erection & Dismantling Work
PESB Engineering Sdn. Bhd.
Completed, Oct 2024